A change order turns "while you're here" into a price.
The customer comes out while you're setting posts and asks for a second gate. You say sure, the crew builds it, and the final invoice lands higher than the number they remember.

The short answer
A change order is a signed note of what changed from the accepted quote, and what that does to the price and the finish date.
Is it a change order? Five calls you'll make on site
Procore, which makes software for builders, defines a change order as a written record of a change to the original scope of work. 3
The detail
That covers work added, substituted or deleted, and its usual reasons include design changes, unexpected job site conditions, and material and crew substitutions. 3 On a small job, they come down to five calls.
The customer asks for something the quote didn't include.
Change order, priced before anyone starts on it.
The detail
This is the "while you're here, could you also..." one. Give the price before you pick up a tool, not on the invoice.
The customer wants something taken out.
Change order, as a credit.
The detail
Credit the part at the price your quote gave it, so the final invoice adds up line by line.
You open it up and find something nobody could have seen.
Change order before you fix it, with photos of what you found.
The detail
Rot behind the siding, a slab where the post hole goes, a buried line. Stop that part of the job, show the customer, write it up, then fix it.
The material you quoted isn't available, so you swap it.
Change order, even when the price doesn't move.
The detail
Same price, different product is still a change to what they're getting. Their signature on the swap ends the argument about the colour before it starts.
You measured wrong, or left a line off the quote.
Not a change order. That one's yours.
The detail
Tell the customer if it moves the finish date, but don't dress your own miss up as their change.
A change order you can copy
Number each one in order on the job, and leave the original quote as it was. Fill the brackets and cut any line your jobs never need.
- Change order #[number] on quote #[number], accepted [date].
- Customer: [name], [site address]. From: [your business], [your name], [phone].
- Asked for by [name] on [date]. Or found on site: [what, where], photos attached.
- The change: [what's added, taken out or swapped, with sizes, materials and colours].
- Price of this change: [add / credit] $[amount] before tax. Materials $[ ]. Labour [hours] × $[rate] = $[ ].
- GST at [your rate]: $[ ]. This change with tax: $[ ].
- Contract price before this change: $[ ] before tax. After it: $[ ] before tax, $[ ] with tax.
- Finish date before this change: [date]. After it: [new date, or no change].
- Paid: [on the final invoice / with the next payment / $[ ] before we order materials].
- Everything else in the quote stays as written.
- Work on this change starts once both of us have signed.
- Customer: [name], [signature], [date]. For [your business]: [name], [signature], [date].
Houzz Pro's guide asks for the same core: the change, its price broken down by labour and materials, two signatures, and the revised completion date. 1
The detail
The extra lines here, the credit, the running contract total and when it's paid, are the ones that stop the argument at the end of the job.
Pricing one change: a gate on, lattice off
Price a change with the rates you used on the quote, and put the sum on the change order itself.
The detail
A customer who can follow the arithmetic has less to argue with. A change can lower the price as well as raise it; write those too.
Example
- Your Landscaping Co., made up for this example, quoted a cedar fence at $14,800 before GST, and the customer said yes.
- On day two they ask for a second gate, and no lattice on the back 12 metres.
- The gate: $515 in posts, gate and hardware, plus 3 hours at your $85 rate, so $515 + (3 × $85) = $515 + $255 = $770.
- The lattice comes off at the quote's own $30 a metre: 12 × $30 = $360, as a credit.
- Net change: $770 − $360 = $410 before tax.
- GST at 5%, the rate in Alberta: 2 $410 × 0.05 = $20.50, so this change is $430.50 with tax.
The detail
New contract price: $14,800 + $410 = $15,210 before tax, and $15,210 × 1.05 = $15,970.50 with GST. 2 Check it the other way: the original $14,800 × 1.05 = $15,540, plus the change's $430.50, is $15,970.50. The finish date moves a day for the gate, and that goes on the change order too. Only the GST rate is real here. Outside Alberta, use your province's rate from the same CRA table.
What Alberta tells your customer to look for
Alberta's page for people hiring a contractor tells homeowners to give any change to the contract their written approval. 4
The detail
It also tells them to get a signed statement from the contractor giving the increase or reduction in cost. 4 So a customer who has read it expects your signature as well as theirs, and the amount as a plus or a minus, not only a new total. The template above does both.
If the customer is borrowing to pay for the job, ask whether the lender has to approve changes too.
The detail
The same page tells homeowners who are borrowing to find that out. 4 Better to know before you order the second gate than while you wait for the money.
When they ask in the driveway
Don't price it out loud You
Say "let me write that up" rather than a number off the top of your head.
The detail
A number said in the driveway becomes the number they remember.
Write it the same day You
Fill in the template while the details are fresh, with photos if you found something.
Get both signatures A system
On paper, or as a document they can sign on their phone.
The detail
Whatever you use, keep it where you'll find it when the final invoice goes out.
Hold the changed part until it's signed You
Keep the crew on the rest of the job, and leave the extra until the yes comes back.
Keep a running total You
The quote, plus or minus each change order by number, should equal the final invoice.
The detail
If it doesn't, find out why before the customer does.
Where we fit
On the systems we build and run, a change is priced like any quote: Otto drafts it from your price list, and it goes to the customer in your name only after you've said yes.
The detail
Otto never signs anything. If the template above does the job, use the template.
Sources
- Free Template: Complete Guide to Construction Change Orders, Houzz Pro (Houzz Inc.), 2023-03-21. Read 2026-10-30. Back
- GST/HST provincial rates table, Canada Revenue Agency. Read 2026-10-27. Back
- What is a change order?, Procore Technologies. Read 2026-10-30. Back
- Hiring a contractor, Government of Alberta. Read 2026-10-30. Back
Checked on 2026-10-30.